A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?
| (A) | 18 days |
| (B) | 27 days |
| (C) | 26.67 days |
| (D) | 16 days |
| (E) | 12 days |
Correct Choice (A) Answer (18 days)
Explanatory Answer
If A can do complete a project in 20 days, then A will complete th of the project in a day.
Similarly, B will complete th of the project in a day.
Let the total number of days taken to complete the project be x days.
Then, B would have worked for all x days, while A would have worked for (x – 10) days.
Therefore, A would have completed th of the project and B would have complete th of the project.
i.e.,
Solving for x, we get x = 18.
|